|
Option A
Option A is intended for retrofits where operating hours
are known in advance, stipulated or agreed upon, and where end use capacity,
demand or power level (kW) can be assessed by either:
-
One-Time, In-Situ End-Use Measurement Method. One-time,
in-situ end-use measurements are measurements taken at the site using calibrated
instrumentation. For electrical loads, this type of measurement usually
requires isolating the device to be measured and measuring the electrical
power (RMS Wattage) that the device draws on all phases.
-
Representative Sample Measurement Method. Representative
sample measurements are measurements taken with calibrated instrumentation
on a representative sample of equipment being installed. Representative
sample measurements are appropriate for energy consuming equipment that
does not vary significantly in load and must be taken on similar equipment
model types. Estimates using representative sample measurements and stipulated
consumption may be adversely affected by inaccurate one-time, in-situ measurements
if proper care is not exercised.
-
Representative Manufacturer's Measurement Method. Representative
manufacturer's measurements are measurements published by the manufacturer
of the equipment. In order for such measurements to be valid, they
should be taken with calibrated instruments on a representative sample
of equipment being installed. Estimates using manufacturer's sample measurements
and stipulated consumption may be adversely affected by the same factors
as one-time, in-situ measurements.
-
Representative Baseline Power Level Profile Method.
Representative baseline power level profiles are either hourly or 15-minute
measurements taken at the site usually at the whole-facility level or sub-panel
level using portable monitoring equipment. These measurements represent
an aggregate end-use load, e.g., all lighting loads in a facility.
Representative baseline power level profiles capture the in-situ 24-hour
profiles of a group of equipment operating during weekday or weekend modes.
Such measurements are appropriate for non-weather-dependent energy consuming
equipment loads that vary within a 24-hour period, but do not vary daily
by more than plus or minus ten percent (±10%). Example:
weekday/weekend whole-facility lighting. In general, representative
baseline power level profiles can be used to measure weather-independent
loads. Representative baseline power level profiles for weather-dependent
loads should include measurements taken over a long enough period to adequately
characterize the schedule (i.e., weekday/weekend and weather-dependent
characteristics of the end use load).
Energy savings are stipulating by multiplying the difference
between baseline and post-installation measurements by the stipulated hours-of-use
or hourly profiles.
However, these can be adversely affected by the following
factors. Savings stipulations:
-
may vary if there are equipment changes during the retrofit
that affect equipment operating efficiency.
-
may vary if operating settings that affect facility system
performance are changed after measurements are taken.
-
may vary if there is a significant number of lamp outages,
or if the actual operating schedule varies significantly from the stipulated
operating schedule.
-
do not measure cooling interaction or increases in heating
load due to reductions in internal heating caused by improved lighting
system efficiency.
-
may vary when manufacturer’s wattage is used if in-situ lamp-ballast-fixture
temperature is significantly different than standard conditions that manufacturer’s
use for published fixture wattage.
 |